Manitowoc County WI passed unanimous 18-month moratorium Apr 21 after a developer approached three towns with land offers. Swain County NC unanimous 12-month Apr 22. Orange County NC unanimous 1-year Apr 22. Weaverville NC reclassified data centers + crypto as 'noxious uses' Apr 28. Cassville WI rejected an anonymous $1B / 500-acre Driftless proposal. Good Jobs First counts 63 local moratorium actions introduced/considered/adopted in 2026; 54 already passed.
Primary source · Good Jobs First ↗
Why it matters
This is a new strategy/ surface — local-zoning-moratorium-corpus. Every passed moratorium is a 12-18 month freeze that re-shuffles the siting map (away from the moratorium county, toward Texas / SC / GA / NoVa-with-existing-pipeline). For paces.md / landgate.md / transect.md positioning: the structured moratorium-status dataset is exactly the unstructured-text-to-structured-data wedge that fits the AI-native test. Worth a 1-day script: scrape Good Jobs First's tracker, normalize to county FIPS + status + sunset date, plot against active interconnection requests.
Related filings
T+3 PJM bid close Jul 7 / T+3 Lakeland FL first reading Jul 6 9AM / T-6 ERCOT Form W Jul 10 / T+11 PJM auction results Jul 14 / T+16 Lakeland FL final vote Jul 20 / T+23 MD FERC comment deadline Jul 27 / Prince George's MD 2-year moratorium vote queued next week / NY A11560 not delivered to Hochul / 10-day clock not started / 6 deadline windows 24 days
Plain-English rollup of what didn't change over the July 4 weekend and what's coming next week. **ERCOT Batch Zero Form W Part A — T-6 to Thursday July 10.** No change since Thursday. The Interconnecting Large Load Entity (data center operator) must...
T-7 ERCOT ILLE Form W Jul 10 / T-21 Form W step 2 Jul 24 / PJM 2028-29 auction closes Jul 7 / results Jul 14 / price band $175-325 MW-day / 13-state governor pre-negotiated band / MD FERC ratepayer complaint comment deadline Jul 27 extended / NY A11560 not delivered to Hochul / 10-day clock not started / passive enactment plausible / 4 deadline-anchored windows next 24 days
Plain-English background on why the four operational-track deadlines all matter this month. Each of these deadlines drives a specific action by developers, hyperscalers, or state parties, and each represents a concrete moment where Cliff can produce a...
T-8 to Jul 10 ERCOT ILLE Form W deadline / Form W Part A now posted Large Load Integration page / notarized to TSP DSP / miss = 438000 MW proposed queue 89% data centers 3-5 years slower / Jul 24 TSP DSP to ERCOT step 2 / Microsoft Fairwater Mount Pleasant WI fully operational Jun 23 / 3.3B first phase / Brad Smith world's most powerful supercomputer / MISO not PJM / low friction state routing / 550 FTE 10000 construction workers / capex not slowing on T+0 morning / state-vs-federal misalignment produces geographic sorting
Plain-English background on the operational track. Yesterday's newsletter covered the regulatory calendar (VA tax, IL DCIP freeze, FL SB 484, Trump EO 14318, PJM auction open, ERCOT Batch Zero deadlines, Abbott Texas memo). Today's operational read is about...
T-0 Jul 1 2026 / VA $0.011/kWh tax live 12:01 AM SCC collecting / IL DCIP application intake frozen Pritzker fall veto session reform / FL SB 484 live utility cost shift prohibition ≥50 MW full cost of service aquifer permitting tightened / Trump EO 14318 live federal permitting acceleration DC >100 MW or >$500M / IL joins OH AZ ME cluster / VA DEQ water language interim today hard cutover Jan 1 2027 Eastern VA Groundwater Mgmt Area / Data Center Coalition Josh Levi opposed / state-federal misalignment first visible day
Plain-English background. Four separate regulatory clocks all reach 12:01 AM Wednesday July 1, 2026 at the same instant. Three are state-level and point toward friction — they increase cost or reduce access for hyperscalers building in that state. One is...