PJM issued the RFI Apr 16 to LSEs, large load participants, hyperscalers, generation developers, DR/DER aggregators, EDCs, and state commissions. Two-phase backstop procurement for 14.9 GW: bilateral phase Sept-Mar (PJM + Charles River Associates as confidential matchmakers), central procurement in March. RFI results inform the final FERC filing in June.
Primary source · Utility Dive ↗
Why it matters
Add to byog-byong-federal-dockets.md and pjm-er26-1088-co-location.md. The May 4 deadline is the live filing surface for any PJM-territory hyperscaler in your outreach queue — anyone serious about siting in Virginia / Ohio / PA needs a position on this. PJM as confidential matchmaker is a structural shift: it puts a regulatory body inside the bilateral PPA process, which is where the regulatory-knowledge-graph wedge actually compounds.
Related filings
Oracle sued Wisconsin PSC Jun 19 Ozaukee County / challenging April tariff rule / $100M/year financial security / very large customer >20 MW sub-A credit / Oracle BBB / Port Washington $15B 672 acres 1 GW 4 buildings We Energies / statutory-authority + discrimination + due-process theories / parallel administrative reconsideration / first hyperscaler-vs-PSC ratepayer-protection lawsuit / template for VA SCC MD FERC IL DCIP TX SB6 / AWS BBB+ adjacent risk / expected 6-12 months to ruling
Plain-English background on why this lawsuit matters more than a single facility dispute. Multiple states have enacted or are enacting 'ratepayer protection' rules for hyperscaler-scale customers in 2025-2026: Virginia's SCC rate class (approved Nov 2025,...
T-7 ERCOT ILLE Form W Jul 10 / T-21 Form W step 2 Jul 24 / PJM 2028-29 auction closes Jul 7 / results Jul 14 / price band $175-325 MW-day / 13-state governor pre-negotiated band / MD FERC ratepayer complaint comment deadline Jul 27 extended / NY A11560 not delivered to Hochul / 10-day clock not started / passive enactment plausible / 4 deadline-anchored windows next 24 days
Plain-English background on why the four operational-track deadlines all matter this month. Each of these deadlines drives a specific action by developers, hyperscalers, or state parties, and each represents a concrete moment where Cliff can produce a...
Paducah $100B+ NextEra/Brookfield 2 GW gas + 2.6 GW storage + 1.8 GW compute Jul 29 / Nvidia $105B backstop OpenAI 4.25 GW PORTS-Pike Ohio Aug 17 / Savannah River Amentum 1 GW + 2 GW gas / BLM first public-land approval appealed / EPA islanded BTM Acid Rain exemption Jul 16 + 60-day NOI / DOE 202(c) SPP + JH Campbell extended / 3 NIETCs canceled Aug 12 / six-RTO show-cause answers due TODAY Aug 17 all asked +3 months / Pledge 200+ utilities 23 governors / S.4214 0 cosponsors HR9442 13 / NoVA 3.8 GW trip Jul 22 largest in PJM history
The Trump administration's answer to the siting war is to route around it: federal land, federal fast-track, and federal emissions accommodation. The federal-site pipeline went from concept to $200B+ in five weeks. July 29: DOE announced a $100B+...
FERC show cause orders Jun 18 / Section 206 / PJM MISO SPP CAISO ISO-NE NYISO / 30-day informational report Jul 20 / 60-day tariff response Aug 17 / 90-day abeyance request Aug 3 / five reform categories / cost-shift prevention is the big one / colocation + BTMG rules / flexible-load transmission services
Plain-English version. On June 18, 2026, the Federal Energy Regulatory Commission (FERC, the federal regulator with jurisdiction over the interstate transmission grid) used Section 206 of the Federal Power Act to issue what are called 'show-cause orders'...