PGRR145 (Planning Guide Revision Request 145) and NPRR1325 (Nodal Protocol Revision Request 1325) are the two governance instruments that establish ERCOT's 'Batch Zero' large-load interconnection process — PGRR145 sets the planning-guide framework and NPRR1325 operationalizes the Provisional Controllable Load Resource (PCLR) protocol that lets large loads commit to partial-firm + curtailable service in exchange for faster Batch Zero approval. Both were filed March 4, 2026; both are now confirmed cleared at the subcommittee level with Urgent status. Yesterday's newsletter confirmed NPRR1325 cleared PRS on May 6 (also Urgent, also 5/2-amended). Today's update: PGRR145 cleared ROS on May 7 with the same posture (Urgent, recommended approval as 5/2-amended, forwarded to TAC). The PGRR145 issue page activity log dated 5/7/2026 reads in full: 'PGRR145 received a recommendation for approval as amended by the 5/2/26 ERCOT comments. PGRR145 will be forwarded to TAC.' The TAC posture is now exactly identical for both items — both carry Urgent flag, both reference the same 5/2 ERCOT comment package, both await TAC May 19-20. The original ERCOT-published timeline (PRS May 6 → ROS May 7 → TAC May 19-20 → Board June 1 → effective July 10) is now actively-tracking. Source: ERCOT NPRR1325 and PGRR145 issue pages (mktrules/issues/{NPRR1325, PGRR145}).
Primary source · ERCOT NPRR1325 + PGRR145 issue pages ↗
Why it matters
Three updates. (1) Confirmation of yesterday's pending verification #1 and #2 — both ERCOT companion items have now cleared the subcommittee level on the same Urgent track, and the May 19-20 TAC vote is structurally locked rather than soft-scheduled. The submission-validator's PCLR / PCLR-companion-planning-guide modules need to be feature-complete against the 5/2-amended versions of *both* documents (not just NPRR1325's protocol language) by close-of-business May 18. The PGRR145 5/2 amendments are likely procedural-overlap with NPRR1325's amendments — same comment package, written by the same ERCOT staff — but the planning-guide language has separate definitions for 'Eligible Large Load,' 'Batch Zero Application Window,' and the milestone-fee escalation schedule that the protocol-side NPRR doesn't contain. The Layer-5 product needs to parse both. (2) The 'Urgent on both sides' posture is procedurally aggressive in a way that Cliff's customers should plan for. ERCOT's standard governance cycle for a paired NPRR+PGRR runs 4-6 months from filing to effective date; the Batch Zero pair is on track for ~4 months (March 4 filing → July 10 effective) which is the fast end of the cycle. The Urgent-on-both-sides pattern means stakeholder objection at TAC has a structurally higher bar — TAC by ERCOT bylaw is supposed to defer to PRS and ROS recommendations on Urgent items unless there's a reliability-implication objection that wasn't surfaced at subcommittee. The realistic risk profile for May 19-20: TAC approves both as recommended (highest probability), TAC remands one item back to subcommittee for additional comment (lower probability — would push effective date 1-2 months), or TAC rejects (very low probability given Urgent status on both sides). Cliff's customers underwriting Texas sites with Q3-Q4 2026 in-service dates can now plan against a real PCLR effective date of July 10, 2026 with reasonably high confidence. (3) The 5/2-amendment comment package is the new authoritative source for PCLR rules — pull the file overnight from ERCOT's issue-page comment archive and diff against the original 3/4 filing. Specific items to surface: (a) Provisional Curtailment Capacity (PCC) calculation method — original filing used historic-15-min-peak; 5/2 amendments may have moved this to projected-load-curve or a 12-month-rolling-90th-percentile method. (b) Curtailment-trigger-event definition — original filing tied PCLR curtailment to Energy Emergency Alert (EEA) Level 1; 5/2 amendments may have moved this to EEA Level 2 (later trigger, more usage allowed before curtailment), which is what most large-load customers want. (c) The milestone-fee schedule — original filing had application-stage / readiness-stage / commercial-operation-stage fee milestones; 5/2 amendments may have softened the readiness-stage thresholds. The submission-validator's PCLR economics calculator needs to be re-run against whichever of these three (or other) changes the 5/2 package contains, before May 18.
Related filings
ERCOT / Batch Zero / PCLR / June 1 board → July 24 deadline
Plain-English framing: ERCOT runs the Texas grid. It received so many giant new load requests (the queue is over 230 GW, more than 70% data centers) that the normal process — make every project wait years for full transmission upgrades — would freeze the...
EPE Consulting / ERCOT / Zero Emission Grid / Seyfarth Shaw ↗
TX SB 6 / PUCT 25.194 / 75 MW / ERCOT Batch Zero
Plain-English framing: SB 6 is the Texas legislature's response to ERCOT receiving 225 new large-load interconnection requests in 2025 (vs. 152 total from 2022-2024) and tracking ~238.6 GW of large-load requests as of December 2025. The law says: any new load...
PUCT / Perkins Coie / Greenberg Traurig / Bracewell / EPE Consulting / Seyfarth Shaw ↗
Meta Hyperion / 10 gas plants / 7 GW / 30% LA grid expansion
Hyperion is the largest single-site hyperscaler gas-fleet buildout in US history. The 10-gas-plant, 7+ GW figure is roughly 2x the next-largest hyperscaler gas commitment on the public tape (Microsoft's Quincy WA campus, ~3.5 GW gas commitment) and roughly...
Yahoo Finance / The Cool Down / WinBuzzer / EnergyNow / Energy Connects / Utility Dive ↗
ERCOT / Batch Zero tabled May 13 / SB 6 / 410 GW queue
Two parallel Texas tracks. (1) Batch Zero (PGRR145 + NPRR1325) is ERCOT's proposed replacement for the existing one-at-a-time Large Load Interconnection Study (LLIS) process — instead of studying each new large-load request individually, Batch Zero would...