PGRR145 (Planning Guide Revision Request 145) and NPRR1325 (Nodal Protocol Revision Request 1325) are the two governance instruments that establish ERCOT's 'Batch Zero' large-load interconnection process — PGRR145 sets the planning-guide framework and NPRR1325 operationalizes the Provisional Controllable Load Resource (PCLR) protocol that lets large loads commit to partial-firm + curtailable service in exchange for faster Batch Zero approval. Both were filed March 4, 2026; both are now confirmed cleared at the subcommittee level with Urgent status. Yesterday's newsletter confirmed NPRR1325 cleared PRS on May 6 (also Urgent, also 5/2-amended). Today's update: PGRR145 cleared ROS on May 7 with the same posture (Urgent, recommended approval as 5/2-amended, forwarded to TAC). The PGRR145 issue page activity log dated 5/7/2026 reads in full: 'PGRR145 received a recommendation for approval as amended by the 5/2/26 ERCOT comments. PGRR145 will be forwarded to TAC.' The TAC posture is now exactly identical for both items — both carry Urgent flag, both reference the same 5/2 ERCOT comment package, both await TAC May 19-20. The original ERCOT-published timeline (PRS May 6 → ROS May 7 → TAC May 19-20 → Board June 1 → effective July 10) is now actively-tracking. Source: ERCOT NPRR1325 and PGRR145 issue pages (mktrules/issues/{NPRR1325, PGRR145}).
Primary source · ERCOT NPRR1325 + PGRR145 issue pages ↗
Why it matters
Three updates. (1) Confirmation of yesterday's pending verification #1 and #2 — both ERCOT companion items have now cleared the subcommittee level on the same Urgent track, and the May 19-20 TAC vote is structurally locked rather than soft-scheduled. The submission-validator's PCLR / PCLR-companion-planning-guide modules need to be feature-complete against the 5/2-amended versions of *both* documents (not just NPRR1325's protocol language) by close-of-business May 18. The PGRR145 5/2 amendments are likely procedural-overlap with NPRR1325's amendments — same comment package, written by the same ERCOT staff — but the planning-guide language has separate definitions for 'Eligible Large Load,' 'Batch Zero Application Window,' and the milestone-fee escalation schedule that the protocol-side NPRR doesn't contain. The Layer-5 product needs to parse both. (2) The 'Urgent on both sides' posture is procedurally aggressive in a way that Cliff's customers should plan for. ERCOT's standard governance cycle for a paired NPRR+PGRR runs 4-6 months from filing to effective date; the Batch Zero pair is on track for ~4 months (March 4 filing → July 10 effective) which is the fast end of the cycle. The Urgent-on-both-sides pattern means stakeholder objection at TAC has a structurally higher bar — TAC by ERCOT bylaw is supposed to defer to PRS and ROS recommendations on Urgent items unless there's a reliability-implication objection that wasn't surfaced at subcommittee. The realistic risk profile for May 19-20: TAC approves both as recommended (highest probability), TAC remands one item back to subcommittee for additional comment (lower probability — would push effective date 1-2 months), or TAC rejects (very low probability given Urgent status on both sides). Cliff's customers underwriting Texas sites with Q3-Q4 2026 in-service dates can now plan against a real PCLR effective date of July 10, 2026 with reasonably high confidence. (3) The 5/2-amendment comment package is the new authoritative source for PCLR rules — pull the file overnight from ERCOT's issue-page comment archive and diff against the original 3/4 filing. Specific items to surface: (a) Provisional Curtailment Capacity (PCC) calculation method — original filing used historic-15-min-peak; 5/2 amendments may have moved this to projected-load-curve or a 12-month-rolling-90th-percentile method. (b) Curtailment-trigger-event definition — original filing tied PCLR curtailment to Energy Emergency Alert (EEA) Level 1; 5/2 amendments may have moved this to EEA Level 2 (later trigger, more usage allowed before curtailment), which is what most large-load customers want. (c) The milestone-fee schedule — original filing had application-stage / readiness-stage / commercial-operation-stage fee milestones; 5/2 amendments may have softened the readiness-stage thresholds. The submission-validator's PCLR economics calculator needs to be re-run against whichever of these three (or other) changes the 5/2 package contains, before May 18.
Related filings
Exelon cuts high-probability DC load 18→11 GW -40% / pipeline 43→25 GW / ComEd cancels PowerHouse Hillwood 1.8 GW $20B TSA / EXC -3.1% / EIA TX 2027 14%→6% / outlier: FirstEnergy +50% AEP 63→69 GW Dominion 53.8 GW Southern 17 GW Camellia 3.2 GW with 1 GW flexible DR / BofA 230+ GW needed vs 93 GW planned / JLL 25 GW H1 absorption 1% vacancy 66 GW UC 95% pre-let / BNEF +52% 2030 118 GW +83% 2035 194 GW / $11.3M per MW +6% / 499k worker shortfall
On July 30 Exelon became the first major utility to mark its data center pipeline to market: 'high probability' load cut from 18 GW to 11 GW (-40%), total future pipeline from 43 GW to 25 GW, disclosed in the Q2 8-K alongside the state-policy squeeze (NJ...
Abbott Jul 24 joint-memo actions / pay own infrastructure / 3 legislative asks 2027 / Project 58000 4CP→12CP comments Aug 11 adoption by Dec 31 / ride-through Jul 13 / Docket 59220 Crusoe/Ensign 260 MW + 265.5 MW wind uncapped curtailment first §39.169 test / Amazon GW Ranch 7.65 GW Pecos County off-grid largest TX BTM / NRG 1.2 GW BYOP CCGT / Energy Vault 1.25 GW BESS+gensets
While the audit froze the front door, the rest of the Texas architecture kept assembling. Abbott's July 17 PUCT/ERCOT joint memo produced its public actions July 24: data centers pay for their own infrastructure, residential ratepayers get shielded from...
Batch Zero 326 projects 205 GW filed by Jul 10 / 2x projection / ERCOT queue 474 GW ~90% DC / all-time peak ~87,533 MW Jul 21 (verified; ERCOT deck said 91,089) / Abbott Aug 3 comprehensive audit = de facto freeze / M-A080326-01 suspends Aug 7 classification / good-cause exception Aug 20 PUCT / Aug 14 special meeting 250-300 projects under 9 months / EIA cuts TX 2027 growth 14%→6%
Form W Part A closed July 10 as scheduled, and the numbers came back science-fictional: 326 study-eligible projects totaling ~205 GW entered Batch Zero — roughly double the ~100 GW ERCOT had projected. On July 29, CEO Pablo Vegas told the Texas Senate...
PJM board letter Jul 27 / CIFP dead none of 11 concepts 2/3 / backstop auction ER26-3380 $555/MW-day 15-yr / IRAS ER26-3515 filed Aug 13 / new ≥50 MW loads post-Jun-2027 without new capacity curtailed FIRST / excluded from RPM 2029/30 / Large Load Registry / Swett 'grave legitimacy crisis' Sept ultimatum / EL26-67 abeyance / ~70 GW new load by 2038 vs 15 GW retired
The stakeholder process failed first: none of the 11 'Immediate Resource Adequacy Solutions' concepts reached two-thirds support, so on July 27 the Board of Managers (Chair Paula Conboy) simply decided. Four planks. (1) Reliability Backstop Procurement — a...