Plain-English framing. Edmond is a Oklahoma City suburb operating under Article XVIII home rule. The city has no pending data center applications and no announced projects. The council voted to pause anyway, expressly to give staff time to 'fully research data centers' impact on Edmond water and electricity, update zoning code, and understand the cost recovery for water, electricity and other infrastructure needed to serve data centers.' The political quote from Ward 2 Councilman Barry Moore is the analytical signal: he 'didn't want the division and anger he'd seen what it's done in other communities.' That is moratorium-by-contagion — passing a freeze not because something is happening locally, but because the council doesn't want the political experience of the freeze fights happening elsewhere. The explicit naming of utility cost recovery as a study item is unusual. Most county moratoriums list water and traffic and noise; very few list 'cost recovery' as a research scope. That language signals Edmond is paying attention to the AEP Ohio and Oregon tariff debates and intends to write a local ordinance that interacts with whatever Oklahoma's PUC eventually does.
Primary source · Edmond city government / NonDoc ↗
Why it matters
Preemptive moratoriums (no proposed project) are now measurable as a distinct category — they signal that the moratorium map is no longer reactive (each freeze responding to a local project) but contagious (each freeze responding to other freezes elsewhere). For outreach and product positioning, the implication is that the de-rate / interruptible-load / disclosure-checklist pitch now lands in places that have never seen a single data center proposal. Cliff's GTM has to widen the prospect list to include cities/counties acting on reputation rather than on real applications.
Related filings
Data Center Watch Q1 2026 report $130B blocked/delayed 3 months matches all 2025 / 75+ projects across 49 states / 833 active opposition groups 2.1x from 396 Dec 2025 / 69+ local government bans by May 2026 / 70% Americans oppose nearby DC up from ~50% late 2025 20pp shift 6 months / Seattle 1-year pause 5 projects / WFYI Jul 6 Indiana investigation / 11 counties ordinances / 17+ counties moratoriums / Marshall + Cass permanent bans / ~1/3 of 92 IN counties restrict / state vs local direction divergence IN PA WI
Plain-English framing of why these two data drops together are the story of the last week. Individual moratorium votes and lawsuits are anecdotes; the macro numbers tell you whether the anecdotes are a scattered pattern or a directional trend. Both data drops...
FERC show cause orders Jun 18 / Section 206 / PJM MISO SPP CAISO ISO-NE NYISO / 30-day informational report Jul 20 / 60-day tariff response Aug 17 / 90-day abeyance request Aug 3 / five reform categories / cost-shift prevention is the big one / colocation + BTMG rules / flexible-load transmission services
Plain-English version. On June 18, 2026, the Federal Energy Regulatory Commission (FERC, the federal regulator with jurisdiction over the interstate transmission grid) used Section 206 of the Federal Power Act to issue what are called 'show-cause orders'...
20MW threshold convergence / NY S.10642 + AOC HR + Sanders S.4214 + FERC RM26-4-000 / forming model-bill consensus / sweeps in wholesale colo + hyperscaler leased capacity / not just marquee campuses
Plain-English version. Until June 24, the most common threshold for state and local data-center legislation was either 100 MW+ (hyperscale conventional definition, used by industry groups like AFCOM and Uptime Institute) or no threshold at all (county...
Hill County TX / moratorium rescinded / RCM Hill $100M suit / disclosure checklist
Plain-English framing. There are two kinds of local government in the U.S. — home-rule (broad authority to legislate locally unless state law specifically forbids it) and Dillon's-rule (only the powers state law expressly grants). Texas counties are...
Texas Tribune / KWTX / KERA News ↗