Plain-English framing. 'Behind the meter' (BTM) means generation that sits on the customer's side of the utility meter and never injects power into the grid. It bypasses every interconnection-queue rule, every capacity-market rule, every transmission-cost allocation — because legally the customer is generating its own power, not buying retail electricity. The trade-off is air permits: a 200 MW gas plant has very large NOx, CO, and PM emissions and has to qualify for either a Title V (major source) or synthetic minor permit under the Clean Air Act. What the Ohio Power Siting Board (OPSB) approval covers. OPSB is the state-level siting authority for power generation. Its approval establishes the location, footprint, and operational envelope but does not itself grant the air permit — that's a separate Ohio EPA process. The fact that OPSB approved on June 9 means the air permit was either already in hand or far enough along that OPSB was comfortable. The plant is two combustion-turbine + reciprocating-engine generation sites, each 200 MW (so 400 MW at full build). Why this is the build-around-the-moratorium pattern. The Ohio site never connects to the grid, so Ohio's grid-side rules and PJM's interconnection queue (which is currently jammed) don't touch it. The data center it serves (Meta's New Albany Sidecat campus) sees its electricity as 'on-site own generation,' which doesn't trip the Ohio PUC's data-center-rate-class triggers, the PJM grid-interconnection queue, or the proposed FERC RM26-4 large-load rules. The constraint that does matter is the air permit and the 24-inch gas pipeline supply — which is why Williams' pipeline subsidiary is the developer.
Primary source · DCD / Power Magazine / Power Engineering ↗
Why it matters
Air-permit / interruptible-load math is Cliff's stated near-term beachhead — and this approval is one of the cleanest live examples of how the BTM gas path is being legally constructed. Three datapoints to extract for the regulatory knowledge graph: (1) The Will-Power OH ↔ Sidecat LLC contract structure (Williams pipeline subsidiary as developer, Meta affiliate as customer) is the template for every hyperscaler-BTM deal coming through the PJM and ERCOT Title V queues — Cliff should source the OPSB filing docket for the actual contract terms. (2) The OPSB approval order is reusable as an exemplar for every Cliff client filing a similar BTM siting application; the language separating 'siting board jurisdiction' from 'air permit jurisdiction' is the kind of procedural template the LLM-ingested wiki should hold. (3) The 24-inch pipeline supply requirement is the constraint that limits this pattern's geographic spread — most ERCOT and PJM sites don't have 24-inch existing service, so the BTM-gas path is concentrated where Williams, Energy Transfer, and Enterprise have midstream backbone. The CRM should flag any Cliff prospect on a midstream-served site as a BTM-gas opportunity specifically.
Related filings
T-0 Jul 1 2026 / VA $0.011/kWh tax live 12:01 AM SCC collecting / IL DCIP application intake frozen Pritzker fall veto session reform / FL SB 484 live utility cost shift prohibition ≥50 MW full cost of service aquifer permitting tightened / Trump EO 14318 live federal permitting acceleration DC >100 MW or >$500M / IL joins OH AZ ME cluster / VA DEQ water language interim today hard cutover Jan 1 2027 Eastern VA Groundwater Mgmt Area / Data Center Coalition Josh Levi opposed / state-federal misalignment first visible day
Plain-English background. Four separate regulatory clocks all reach 12:01 AM Wednesday July 1, 2026 at the same instant. Three are state-level and point toward friction — they increase cost or reduce access for hyperscalers building in that state. One is...
EPA May 11 / NSR 'begin actual construction' / 45-day comment / air permit timing restructure
Plain-English framing. The Clean Air Act's New Source Review (NSR) program requires that a 'major source' of air pollution obtain a pre-construction permit before construction begins. The phrase 'begin actual construction' has been interpreted (since the 1980...
EPA proposed rule / Gibson Dunn / Butler Snow / Inside Climate News / Troutman Pepper Locke ↗
PA + OR + WI + FL / 14-day cluster
Three regulatory events in the same 24-hour window on May 8 — Pennsylvania PUC's model-tariff vote, PPL Electric's pending rate-case settlement (filed March 13, ALJ recommendation April 17, effective July 1), and Oregon PUC's PGE Schedule 96 directive —...
WHYY / WESA / Utility Dive / KGW / KOIN / Beaver County Radio / RTO Insider ↗
Denver / Cheyenne / Charlotte / Cave City / PJM compliance
Today is the single highest-density 'moratorium decision day' of 2026 so far. Four municipal-level decisions in geographically distinct markets (Mountain West urban, Sun Belt urban, central Kentucky rural, Mountain West regional capital) plus a structurally...