Permitting · live
A 12-state audit of organic search results for 'data center permitting' showed law firms weakly holding one slot and tracker sites filling the rest — permit consultants, the people actually doing the work, are structurally silent because they cannot cite clients without burning airshed competitors. Cliff can publish because it is a platform, not a retained advisor. Five states live now; more as deadlines cluster.
Live state pages
Virginia’s Tier IV mandate, Texas’s PUCT 58481 final rule, Ohio’s ballot signature deadline, and Illinois’s tax-exemption freeze all land on July 1, 2026. This is not coordination; it is what happens when four state legislatures react to the same 2025-2026 hyperscaler buildout at once.
PJM · 15 bills signed
HB 507 Tier IV generator mandate takes effect Jul 1, 2026. APG-578 curtailment memo controls de-rate.
Next deadline
Jul 1, 2026
Binding instrument
DEQ APG-578 · HB 507
Open live page →
ERCOT · live grid
PUCT 58481 final rule expected Jul 1. Batch Zero PCLR elections active through summer. Live ERCOT grid on the page.
Next deadline
Jul 1, 2026
Binding instrument
16 TAC §25.194 · SB 6
Open live page →
PJM · ballot initiative
Constitutional 25 MW cap amendment on the Nov ballot if 413,488 signatures clear by Jul 1, 2026.
Next deadline
Jul 1, 2026
Binding instrument
Ballot 2026 · HB 646
Open live page →
PJM + MISO · tax freeze
Pritzker's two-year sales-tax exemption suspension effective Jul 1. POWER Act (SB 4016) targets 50 MW+.
Next deadline
Jul 1, 2026
Binding instrument
Pritzker EO · SB 4016
Open live page →
Southern Co · PSC split
DeKalb hearing May 12; moratorium expires Jun 23. SELC challenge on the Georgia Power data center plan pending rehearing.
Next deadline
May 12, 2026
Binding instrument
DeKalb text amendment · PSC
Open live page →
How each page is maintained
Every state page ingests filings, bills, and ordinances from the underlying docket corpus: PUC/PSC orders, DEQ/EPD guidance, state-agency rulemakings, and county text amendments. An LLM extracts material facts, parties, deadlines, and regulatory citations into a structured record. The pages render from that record with explicit “as of” timestamps and next-refresh timers.
Texas adds live ERCOT grid state on top (system load, HB_NORTH LMP, grid condition) because the operational picture swings the underwriting. Other states get the live countdown and ticking “last verified” until their own grid feeds are wired in.
Working on a state that isn’t on the list? Tell us at /contact. Next states in the backlog: North Carolina, Arizona, Oregon, Iowa, Tennessee, Indiana, Nevada.