Charlotte NC / 11-0 / 150-day / Nov 5 expiry
Charlotte City Council passed a 150-day moratorium on new data centers June 8, 2026 by an 11-0 unanimous vote — the largest banking and finance city in the Carolinas, with 35 existing data centers in city limits and 93 across the state, now joining DeKalb GA and Seattle as the third major metro-area moratorium in a week
Plain-English framing. Charlotte is the second-biggest US banking center after New York (Bank of America HQ, Truist HQ, Wells Fargo's east coast hub) and the dominant Carolina metro. Until this week the assumption was that bank-anchored cities would be friendly to data center buildouts because financial-services tenants overlap heavily with the demand. That assumption broke 11-0.
The moratorium runs through November 5, 2026. It exempts any project with valid building permits or 'substantial expenditures already made in good faith' — most notably the first phase of PowerHouse Charlotte (the University City area campus). City staff will use the 150 days to draft new zoning regulations covering noise, water draw, and electric infrastructure cost recovery. The political driver was resident testimony at recent council hearings citing noise from existing facilities and rising utility costs.
North Carolina has 93 data centers operating today, 35 of them in Charlotte. That's the highest concentration in the Southeast outside of Northern Virginia. The state is also where Duke Energy's Public Staff filed last week for a mandatory 50 MW / 80% load factor tariff (covered in the June 10 digest). So Charlotte's moratorium and the Duke state-level tariff filing are now stacked on the same developer in the same week.
Axios Charlotte / WBTV / WCNC ↗
Why it matters
Charlotte is the first major banking metro to enact a moratorium. That breaks the 'finance-anchored cities will stay developer-friendly' assumption — Cliff's siting tool should now treat banking-hub metros (Phoenix, Dallas, Atlanta, Charlotte, Minneapolis) as moratorium-risk-eligible, not as safe zones. The 35-DCs-already-in-city baseline is also the new precedent for 'mature market that pulled the brake': Loudoun County and Phoenix should expect similar pressure when their council compositions shift.
VirginiaNorth CarolinaWashingtonArizonaMoratorium
Spokane WA / 1-yr moratorium / Avista trigger / 500 MW MOU
Spokane City Council members Paul Dillon, Sarah Dixit, and Kate Telis introduced an emergency one-year citywide moratorium ordinance on June 10, 2026 — vote scheduled for June 15 — one day after Avista confirmed a non-binding MOU with an unnamed data center customer that could grow to 500 MW
Plain-English framing. Spokane is the second-largest city in Washington State, served by Avista Corp — a small investor-owned utility (about 400,000 electric customers in eastern Washington plus northern Idaho) whose total system load is roughly 1,000 MW. So when Avista signed a non-binding MOU on June 3 to provide 125 MW starting in 2029 with potential expansion to 500 MW by 2032, that one customer would equal about half of all current Spokane County residential and business customers combined.
The MOU was disclosed in stages. On June 3 Avista confirmed 'a large load customer' without naming the industry. On June 9 it confirmed the customer is a data center. The proposed location remains confidential under the MOU's NDA. A Change.org petition opposing the project launched almost immediately. One day after the confirmation, the three council members filed the moratorium ordinance.
The ordinance would freeze acceptance, processing, review, and approval of any new data center building permit applications for one year while the city updates its Comprehensive Plan, Water Conservation Plan, Water System Plan, and economic development strategy. Mayor Lisa Brown publicly supported the freeze, stating Spokane 'does not currently have the necessary framework to site and permit data centers.'
Spokesman-Review / City of Spokane / KXLY ↗
Why it matters
Spokane is the inverse of Charlotte — moratorium triggered by a single MOU disclosure, not by accumulated frustration. That makes the access-disclosure sequence itself the political flashpoint. Avista chose stages (June 3 vague → June 9 specific → confidential location). Each step compounded resident reaction. Pre-development diligence playbooks need to model this: in mid-size utility service areas, every disclosure step is a moratorium-trigger event, and developers should price NDA carve-outs and joint announcement frameworks into the early-stage deal terms with the utility.
North CarolinaWashingtonMoratorium
Homewood AL / preemptive / Birmingham-metro third freeze
Homewood, AL Mayor Jennifer Andress publicly announced June 11, 2026 she will push the City Council for a preemptive moratorium at the June 22 meeting — no current data center proposals exist in Homewood; the move follows Birmingham's 6-month moratorium and Leeds's one-year freeze in the same Birmingham metro
Plain-English framing. Homewood is an inner-ring suburb of Birmingham, Alabama (population ~26,000, sits inside the I-65 / I-459 ring). Birmingham itself passed a 6-month moratorium in late May and Leeds (eastern Birmingham metro) approved a one-year freeze. Now Homewood's mayor wants to add a third Birmingham-metro freeze before any developer has even submitted a sketch plan.
Mayor Andress's stated reasoning is operationally specific — she explicitly listed 'noise regulations, utility consumption, cooling aspects, and chemicals that go in the water' as the four areas the city's zoning code does not currently address. She also tied the moratorium proposal to Homewood's existing comprehensive plan rewrite, which is already scheduled to complete inside 12 months. So the moratorium becomes a parallel work-stream against an already-funded planning timeline rather than a one-off pause.
Alabama is a Dillon's Rule state for municipalities (cities can only act under powers specifically granted by state law), which means each moratorium has to clear the same Title 11 zoning-authority threshold. The fact that three Birmingham-metro cities are clearing it in the same quarter suggests a regional template is emerging — Cliff should expect the rest of the Birmingham metro (Hoover, Vestavia Hills, Mountain Brook) to follow the same playbook within 90 days.
WBRC / CBS 42 / City of Homewood ↗
Why it matters
Birmingham metro is now the densest moratorium cluster in the country — three cities frozen in one quarter, two of them preemptive (no application filed). That's a real signal that 'preemptive' is becoming a contagion category in its own right, separate from reactive freezes triggered by an actual proposal. For Cliff's moratorium tracker, the Birmingham cluster should be the prototype for the 'metro-area cascade' field — once two cities in a metro freeze, the rest of the metro should be flagged as 90-day-likely candidates.
North CarolinaMoratoriumHyperscaler