Dominion Energy reported Q1 2026 operating EPS $0.95 vs $0.86 consensus, revenue $5.02B vs $4.47B. Commercial sales +8.4% YoY led by data centers; weather-normalized sales +4.3% LTM. Total contracted data center capacity reached ~51 GW as of March 2026, a ~2.5 GW increase from December (~5% QoQ) and more than tripling from 16.5 GW in July 2023. Contract stack: 29.5 GW under SELOA (Substation Engineering Letter of Authorization), 11.1 GW under CLOA (Construction Letter of Authorization), 10.4 GW under ESA (Electric Service Agreement) — ESA tier carries take-or-pay revenue obligation regardless of whether the customer takes service. PJM separately awarded Dominion $5B in transmission projects, the largest ever granted to Dominion Virginia. CFO Steven Ridge: demand is 'accelerating and durable' from 'differentiated high quality, low risk' data center customers. Affirmed 2026 EPS guidance $3.45–$3.69, 5–7% LT growth biased to upper end from 2028.
Primary source · Dominion Energy Q1 2026 earnings (Investing.com) ↗
Why it matters
This is the supply-side companion to yesterday's $725B hyperscaler capex sweep. The 51 GW contracted figure is the largest single-utility data center book in the country and the cleanest validation that hyperscaler capex is landing physically in PJM-East. Contract-stack discipline matters: SELOA → CLOA → ESA is a maturity ladder, and ESA carries take-or-pay — i.e., Dominion is not absorbing speculative load. Useful for the firm-equivalent-mw-underwrite.md framework: the SELOA / CLOA / ESA progression is exactly the kind of contract maturity tagging the de-rate calculator needs to model — a 30 GW SELOA pipeline doesn't underwrite the same way as a 10 GW ESA book. Add a row to virginia-data-center-legislation-2026.md showing that 51 GW contracted is the denominator the legislature is fighting over in the HB 1393 / SB 253 cost-shift mechanism (next item). Also: Dominion's contracted-capacity disclosure cadence (quarterly, with ~5% QoQ growth) is something the regulatory-knowledge-graph should ingest as a structured-data feed — every other utility serving hyperscalers is going to be pressured to disclose at the same granularity by mid-2026.
Related filings
Prince George's County MD 2-year statutory moratorium / expected vote today Tue Jul 7 / Chair Krystal Oriadha says has votes not unanimous / replaces Braveboy EO expiring Sep 30 / 11-member council 6 needed / 2nd most populous MD county 955k / adjacent to DC / diversification-away-from-VA siting site / with Montgomery + Washington ~40% MD population under 12+ mo freeze / effective statewide MD removal through 2028 / fourth pattern county-cluster-reaches-critical-mass
Plain-English background on why the Prince George's vote today matters as more than a local ordinance. Prince George's County is the second-largest county in Maryland by population (~955k residents), immediately east of Washington DC. It sits inside the PJM...
PJM 2028/29 capacity auction bid close today Jul 7 EOD / results Tue Jul 14 after 4 PM ET / governor-negotiated $175 floor $325 cap / 13-state pre-negotiated band first-in-history / 65M people served / 22% of US demand / Virginia data center alley in-footprint / 2024/25 cleared $28.92 / 2025/26 cleared $269.92 / 2026/27 cleared $329.17 cap / clearing outcome determines 2028+ hyperscaler capex modeling / same-day analysis window 3-6 PM ET Jul 14
Plain-English background on why the PJM 2028/29 auction closing today matters more than a routine capacity procurement. PJM Interconnection operates the regional grid across 13 states and DC (roughly PA/NJ/MD/DE/VA/WV/OH/IL/IN/KY/NC/TN/MI and DC) — 65 million...
Oracle sued Wisconsin PSC Jun 19 Ozaukee County / challenging April tariff rule / $100M/year financial security / very large customer >20 MW sub-A credit / Oracle BBB / Port Washington $15B 672 acres 1 GW 4 buildings We Energies / statutory-authority + discrimination + due-process theories / parallel administrative reconsideration / first hyperscaler-vs-PSC ratepayer-protection lawsuit / template for VA SCC MD FERC IL DCIP TX SB6 / AWS BBB+ adjacent risk / expected 6-12 months to ruling
Plain-English background on why this lawsuit matters more than a single facility dispute. Multiple states have enacted or are enacting 'ratepayer protection' rules for hyperscaler-scale customers in 2025-2026: Virginia's SCC rate class (approved Nov 2025,...
T-7 ERCOT ILLE Form W Jul 10 / T-21 Form W step 2 Jul 24 / PJM 2028-29 auction closes Jul 7 / results Jul 14 / price band $175-325 MW-day / 13-state governor pre-negotiated band / MD FERC ratepayer complaint comment deadline Jul 27 extended / NY A11560 not delivered to Hochul / 10-day clock not started / passive enactment plausible / 4 deadline-anchored windows next 24 days
Plain-English background on why the four operational-track deadlines all matter this month. Each of these deadlines drives a specific action by developers, hyperscalers, or state parties, and each represents a concrete moment where Cliff can produce a...