Bloomberg, DCD, and CoStar all confirmed April 29–30 that Compass Datacenters is pulling out of the Prince William Digital Gateway data center corridor in Northern Virginia. Sequence: Virginia Court of Appeals blocked the project March 31 after years of litigation; Prince William County Board of Supervisors voted April 14 to stop defending the rezoning; Compass's attorney told reporters last week the company will not appeal. Compass and QTS were the two co-developers of the 2,100-acre / 37-data-center corridor along Pageland Lane. QTS is separately appealing the parallel ruling to the Virginia Supreme Court (yesterday's coverage). Compass is owned by Brookfield Asset Management. Quartz reports residents who had signed land-use contracts with QTS are now suing to get out.
Primary source · Bloomberg ↗
Why it matters
This is the cleanest 'years of soft-cost spend voided by a court ruling' data point Cliff has — Compass and QTS reportedly invested 'tens of millions of dollars' across years of approvals, and the AI-paperwork-automation market research already tracks PW Digital Gateway as $54M/yr CBA voided 2025 in the host-agreement table. Two new things to add to ai-paperwork-automation-market-research.md: (1) the Brookfield exit confirms the Compass-side losses are not litigated-recoverable — Brookfield wrote down the soft costs rather than appeal, which sets a precedent for how institutional capital marks similar entitlement risk on the rest of the NoVa pipeline. The implied per-acre soft-cost loss across the 2,100 acres is on the order of $20–40K/acre for Compass's share, a clean upper bound on hyperscale-corridor entitlement-risk exposure. (2) The QTS appeal continuing while Compass exits is the first observable bifurcation between two co-developers on the same corridor — QTS is taking a different risk view than Brookfield/Compass, which materially affects how the VA Supreme Court reads the case (one defendant, not two, with mixed standing). For the ercot-large-load-underwriting and de-rate-calculator GTM: this is the canonical example of why submission-readiness underwriting needs to model not just procedural compliance but the political-economy chokepoint in the appeals process — a 27-hour hearing voided a 2-year approval, and the appeals path took another 8 months to fully unwind. That timeline (procedural defects alleged → trial court invalidation → appellate confirmation → board stops defending → developer walks) is now the canonical worst-case for VA hyperscale entitlement, and it's directly inputtable into the de-rate calculator's regulatory-risk module.
Related filings
Meta Hyperion / 10 gas plants / 7 GW / 30% LA grid expansion
Hyperion is the largest single-site hyperscaler gas-fleet buildout in US history. The 10-gas-plant, 7+ GW figure is roughly 2x the next-largest hyperscaler gas commitment on the public tape (Microsoft's Quincy WA campus, ~3.5 GW gas commitment) and roughly...
Yahoo Finance / The Cool Down / WinBuzzer / EnergyNow / Energy Connects / Utility Dive ↗
WY / Cheyenne / first Mountain West moratorium / 70-project pipeline
Cheyenne is the first city anywhere west of the Mississippi to introduce a data-center moratorium ordinance at the council level in 2026 (the Wisconsin/Michigan/Ohio/Indiana cluster is Midwest; the GA/NC/FL/AL cluster is Sun Belt; Texas has no moratorium tape...
Cowboy State Daily / KGAB / Cap City News / Wyoming News / Casper Star-Tribune ↗
CO HB 1030 / killed 11-2
HB 1030 was Colorado's primary 2026 attempt to attract data-center investment via tax incentives — the bill was first introduced in January and modeled loosely on the sales-and-use exemption regimes that Texas, Virginia, Georgia, Ohio, Iowa, Nebraska, and...
KUNC / CPR News / The Colorado Sun / The Durango Herald ↗
NC / HB 1004
WRAL and Data Center Knowledge confirm North Carolina lawmakers have moved HB 1004, the Ratepayer and Resource Protection Act, into the 2025-2026 General Assembly. Filed April 27, 2026. Threshold: facilities with peak electricity demand of ≥40 MW...