PJM Inside Lines and Utility Dive both confirmed April 29 that 811 new generation projects representing 220 GW of nameplate capacity have entered PJM's first interconnection cycle since the queue was paused for reform in 2022. Mix by fuel: gas-fired 106 GW (largest), battery storage 67 GW, nuclear 18 GW, solar 15 GW, solar-storage hybrid 9 GW, wind 5 GW. PJM separately filed an Expedited Interconnection Track (EIT) with FERC on February 27 that would let up to 10 generating projects per year skip the queue entirely with executed GIAs in approximately 10 months, conditioned on committed commercial in-service dates and state-siting-authority support. PJM has requested EIT effectiveness by July 31, 2026.
Primary source · Utility Dive ↗
Why it matters
Three signals worth tracking in the regulatory-knowledge-graph and gas-feasibility page: (1) 106 GW of gas-fired in the new queue is roughly 10x the typical PJM gas-tied additions in a normal cycle and almost certainly contains a large share of co-located / data-center-tied generation rather than utility-procured capacity — meaning the new PJM queue is structurally a data-center-power buildout, not a generation-mix transition. The headline implication for Cliff is that gas-feasibility consolidation page becomes the right surface to model: which states' new-build gas-tied projects clear PJM's revised queue process versus get held up at state air permit / siting authority. (2) 18 GW of nuclear in the queue is the largest nuclear surge in the PJM queue history and almost entirely SMR / advanced-reactor proposals — a tell that the Vistra / Talen / Constellation co-location-with-existing-nuclear playbook has triggered a new-build-nuclear cohort that didn't exist 18 months ago. (3) The Expedited Interconnection Track is the structurally important piece for Cliff's developer-financing capital stack — 10 projects per year with state-siting-authority support is the explicit route by which a hyperscaler with state-political-capital can short-circuit the standard 4–6 year PJM queue. The state-siting-authority gate is exactly the political-economy chokepoint that's becoming the binding constraint as local moratoriums proliferate; an EIT-ineligible site is now a separate de-rate input. The April 29 queue reopening is the real demand-side data point that monetizes against the May 4 RFI's 14.9 GW backstop number — the queue tells you what gets built, the RFI tells you what PJM will buy if the queue under-delivers.
Related filings
Ohio Socrates South / 200 MW BTM gas / Williams + Meta / approved Jun 9 / build-around pattern
Plain-English framing. 'Behind the meter' (BTM) means generation that sits on the customer's side of the utility meter and never injects power into the grid. It bypasses every interconnection-queue rule, every capacity-market rule, every transmission-cost...
DCD / Power Magazine / Power Engineering ↗
Prince George's County MD 2-year statutory moratorium / expected vote today Tue Jul 7 / Chair Krystal Oriadha says has votes not unanimous / replaces Braveboy EO expiring Sep 30 / 11-member council 6 needed / 2nd most populous MD county 955k / adjacent to DC / diversification-away-from-VA siting site / with Montgomery + Washington ~40% MD population under 12+ mo freeze / effective statewide MD removal through 2028 / fourth pattern county-cluster-reaches-critical-mass
Plain-English background on why the Prince George's vote today matters as more than a local ordinance. Prince George's County is the second-largest county in Maryland by population (~955k residents), immediately east of Washington DC. It sits inside the PJM...
FERC show cause orders Jun 18 / Section 206 / PJM MISO SPP CAISO ISO-NE NYISO / 30-day informational report Jul 20 / 60-day tariff response Aug 17 / 90-day abeyance request Aug 3 / five reform categories / cost-shift prevention is the big one / colocation + BTMG rules / flexible-load transmission services
Plain-English version. On June 18, 2026, the Federal Energy Regulatory Commission (FERC, the federal regulator with jurisdiction over the interstate transmission grid) used Section 206 of the Federal Power Act to issue what are called 'show-cause orders'...
FL moratorium wave / Clay final + Hernando, Lake first reading Jun 23 / Santa Rosa 3-1 to draft / Zephyrhills final / 5-8 FL jurisdictions in 5 weeks / SB 484 backdrop / water-first concern
Plain-English version of what happened. Tuesday, June 23 was the single most active moratorium day Florida has had — three county boards moved separate ordinances forward in a coordinated wave. Clay County (just south of Jacksonville, ~220,000 residents) gave...