At Monday's contentious Hermantown MN City Council meeting, a Google Technical Infrastructure team representative gave the company's first in-person presentation on the proposed 1.2 million sq ft data-center site. Project disclosures: $650 million for Phase 1, three total phases, total project investment of ~$2 billion over an 8-10 year build-out, 1,500-2,000 highly-paid skilled construction jobs at peak. The crowd was largely union supporters in 'Yes MN' green gear backing the project's economic benefits, but the City Council tabled both the up-to-$80M / 28-year tax-abatement package and the development agreement after hours of public comment. No timeline set for reconsideration. The Stop the Hermantown Data Center lawsuit (filed April 29) remains pending, alleging zoning amendments were 'arbitrary and capricious' and that city administrators signed Google NDAs without prior council approval.
Primary source · MPR News / Northern News Now ↗
Why it matters
Two items to update on yesterday's Hermantown writeup. (1) The disclosed project numbers ($650M / $2B total / 1,500-2,000 jobs) anchor the negotiated-tax-abatement math. The proposed $80M abatement against $2B total spend is a 4.0% effective abatement rate — at the lower end of typical hyperscaler / state-incentive packages (Henrico VA averages 6-8%, Mount Pleasant WI was ~12% on the original Foxconn / now Microsoft package). If NC HB 1004 passes (yesterday's lead) banning local tax incentives entirely for ≥40 MW loads, sites in NC would face an effective +4-12% capital-cost penalty against MN / VA / WI peers — a real geographic-arbitrage delta worth modeling in firm-equivalent-mw-underwrite.md. (2) Three phases over 8-10 years is the disclosure that shifts the lawsuit math. If Google is contractually committed to a 3-phase / 8-10 year buildout, the 'sue-then-table' play (now demonstrated in MN / OH / IL within 30 days) carries a new cost: each year of litigation delay pushes Phase 3 commissioning past Google's AI-capacity-commitment window, which (per Google's own April 2026 capex guidance) is structured around a 2030 baseline. A 2-year delay collapses Phase 3 entirely. That's a real operational risk Google will price into its alternative-site portfolio — and worth tracking whether Google quietly accelerates a backup MN / WI / IA site as a hedge over the next 30-60 days.
Related filings
Hermantown / tabled
After a packed Hermantown City Council meeting Monday night with hours of public comment, Councilor John Geissler moved to table both the tax-abatement and the development agreement for Google's 1.2 million sq ft data center, citing the need for clarity on...
NC / HB 1004
WRAL and Data Center Knowledge confirm North Carolina lawmakers have moved HB 1004, the Ratepayer and Resource Protection Act, into the 2025-2026 General Assembly. Filed April 27, 2026. Threshold: facilities with peak electricity demand of ≥40 MW...
Local litigation
Two parallel local-opposition lawsuits this past week. Yorkville, IL: Preserve our Yorkville & Community filed against the City of Yorkville to halt the 1,034-acre Project Cardinal data center; April 24 court hearing extended to May 8 with both legal teams...
Cheyenne / committee no recommendation / motion died for second
Cheyenne is the weakest of the four outcomes for the pause camp. A motion failing to get a second in committee is the procedural equivalent of zero councilors other than the sponsor being willing to publicly support advancing the proposal. The 'no...
Cap City News / Wyoming News / Cowboy State Daily / Wyoming Public Media ↗