Coweta County is southwest of Atlanta and is the second metro-Atlanta county after DeKalb to pause data centers. The vote was unanimous. Scope is data centers only (no battery storage bundling), but the pause is broad within that scope — it halts new permits, rezonings, conditional uses, variances, and the public hearings that would let any of those move forward. The pattern-relevant detail is the carve-out. Five data center projects already in the Coweta pipeline are exempt from the moratorium, not because the county chose to exempt them, but because Georgia vested-rights law automatically grandfathers projects that have reached a certain point in the entitlement process. The county had no discretion on those five — the statute does the exempting. That is a fundamentally different exemption mechanism than the ones already tracked in the corpus. Boone County Indiana's Meta LEAP carve-out worked through municipal annexation (the parcel left county jurisdiction). Nashville's EO 59 worked through state preemption (state law blocked a clean ban so the executive used other levers). Box Elder Utah's MIDA carve-out worked through a state special authority that bypasses county land use entirely. Coweta's exemption works through statutory vested-rights doctrine, which exists in every state but with very different thresholds for when a project becomes vested.
Primary source · Atlanta Journal-Constitution ↗
Why it matters
Vested-rights is the most consequential of the four exemption pathways because it is automatic and statutory rather than discretionary. The corpus implications are concrete. (1) Every state has its own vested-rights threshold — some trigger at building permit, some at site plan approval, some at substantial investment, and the case law is decades deep. The regulatory graph needs a per-state vested-rights doctrine page that captures the trigger event for each state, because that trigger determines which projects survive a moratorium and which die in it. (2) Per-project metadata has to include 'date of vesting trigger event' alongside the annexation-as-of-date field added yesterday, so a moratorium-impact query can answer not just 'is this parcel inside an annexation' but 'has this project crossed its state's vested-rights threshold yet.' (3) For Coweta specifically, the five exempt projects are now the most strategically valuable parcels in the county for the next six months — they are the only data centers that can move forward, which inverts the usual moratorium-as-deal-killer assumption. That inversion is worth surfacing as a search query: 'show me every vested-but-pre-construction project in a currently-moratoriumed jurisdiction.'
Related filings
Wisconsin cluster / Dane Jun 4 / Superior May / La Crosse Jun 18 / MISO territory / 5000-server 10000-sqft template
Plain-English version of the geographic pattern. The moratorium streak has been geographically dispersed — Iowa, Tennessee, California, Georgia, Nebraska, Utah, North Carolina, Indiana, Oklahoma, Nevada (the counter-signal), Wisconsin. Most states have had at...
WisBusiness / Dane County Board ↗
Data Center Watch Q1 2026 report $130B blocked/delayed 3 months matches all 2025 / 75+ projects across 49 states / 833 active opposition groups 2.1x from 396 Dec 2025 / 69+ local government bans by May 2026 / 70% Americans oppose nearby DC up from ~50% late 2025 20pp shift 6 months / Seattle 1-year pause 5 projects / WFYI Jul 6 Indiana investigation / 11 counties ordinances / 17+ counties moratoriums / Marshall + Cass permanent bans / ~1/3 of 92 IN counties restrict / state vs local direction divergence IN PA WI
Plain-English framing of why these two data drops together are the story of the last week. Individual moratorium votes and lawsuits are anecdotes; the macro numbers tell you whether the anecdotes are a scattered pattern or a directional trend. Both data drops...
Lakeland FL Monday Jul 6 NO VOTE / 3+ hours public comment / 'Project Swan' 60 acres Old Tampa Hwy / postponed first reading to Sun Jul 20 / possible final vote Sun Aug 3 / 2-week slip / postponement signal itself / base rate 40% stronger version 30% original 15% weaker 10% withdrawn 5% delayed / Lakeland Electric city-owned utility / no interconnection headroom stated / Zephyrhills Jun 24 first FL moratorium precedent / FL SB 484 effective Jul 1
Plain-English recap of what actually happened at Lakeland City Hall Monday morning. Commissioners were scheduled to hold a first reading and public hearing on a proposed 12-month moratorium covering any data center or 'large load electric customer' using >50...
MI Penn Twp / IN Washington / FL Nassau / WI Sheboygan
Three more entries in the local-moratorium tape, each illustrating a different sub-pattern. Penn Township MI: pure preemptive moratorium with no land sold and no developer named. The Diamond Lake Association (the local lake-property-owner organization) drove...
WNDU / WSBT / IPM News / Washington Times-Herald / News4Jax / Seehafer News ↗