Plain-English framing. The Ohio Power Siting Board (OPSB) is the state body that issues construction certificates for large generation and transmission projects in Ohio (similar role to a state public utility commission's siting arm). It is separate from PUCO, which sets retail electric tariffs. So a hyperscaler campus that needs BTM generation has to clear both bodies: OPSB to build the plant, PUCO if the campus also takes any grid supply. Meta's New Albany campus is the largest disclosed behind-the-meter gas commitment in the country: two 200 MW plants from Williams Companies (the pipeline major), 10-year supply agreement, total capital cost about $1.6 billion. The Socrates North plant was approved earlier; the June 9 approval is for Socrates South, the second 200 MW unit. Both plants sit on-site, dedicated to the data center, and bypass the grid for the bulk of the campus's load. The broader BTM picture: industry analysts now count roughly 101 GW of behind-the-meter gas capacity announced by hyperscalers nationally, 57 GW with disclosed equipment orders, ~7 GW already under construction, and ~2 GW currently operating across four sites. End-of-2026 forecast is 2.8-3.2 GW operating. The growth curve from 2 GW today to 7+ GW under construction is the leading indicator that BTM is the answer to the grid queue, not just a niche workaround.
Primary source · Data Center Dynamics / Ohio Power Siting Board ↗
Why it matters
OPSB approval is the regulatory checkpoint that mattered. Two state checkpoints stand between an announced BTM project and steel in the ground: OPSB (or equivalent siting authority) plus the state air permit (Title V if PTE crosses 100 tpy NOx, which 200 MW gas does). Williams + Meta have now cleared both for Socrates South. Cliff's BTM underwriting product should add 'state-siting-board status' as a distinct field (Socrates South = approved, hundreds of others still pending), and use the Meta/Williams 10-yr template as the reference contract for sizing customer-funded BTM economics.
Related filings
EPA May 11 / NSR 'begin actual construction' / 45-day comment / air permit timing restructure
Plain-English framing. The Clean Air Act's New Source Review (NSR) program requires that a 'major source' of air pollution obtain a pre-construction permit before construction begins. The phrase 'begin actual construction' has been interpreted (since the 1980...
EPA proposed rule / Gibson Dunn / Butler Snow / Inside Climate News / Troutman Pepper Locke ↗
Ohio Socrates South / 200 MW BTM gas / Williams + Meta / approved Jun 9 / build-around pattern
Plain-English framing. 'Behind the meter' (BTM) means generation that sits on the customer's side of the utility meter and never injects power into the grid. It bypasses every interconnection-queue rule, every capacity-market rule, every transmission-cost...
DCD / Power Magazine / Power Engineering ↗
FERC show cause orders Jun 18 / Section 206 / PJM MISO SPP CAISO ISO-NE NYISO / 30-day informational report Jul 20 / 60-day tariff response Aug 17 / 90-day abeyance request Aug 3 / five reform categories / cost-shift prevention is the big one / colocation + BTMG rules / flexible-load transmission services
Plain-English version. On June 18, 2026, the Federal Energy Regulatory Commission (FERC, the federal regulator with jurisdiction over the interstate transmission grid) used Section 206 of the Federal Power Act to issue what are called 'show-cause orders'...
OpenAI Portsmouth / 10 GW / DOE federal land / SB Energy / NVIDIA credit / state-moratorium bypass
Plain-English framing. The Portsmouth Gaseous Diffusion Plant (or 'Piketon site') is a Cold War-era uranium-enrichment facility on ~1,200 acres of DOE-owned federal land in southern Ohio. It was decommissioned, and the cleanup created a large, fully-graded...
The Reporting Project (Ohio) / DCD / Network World / Scioto Post ↗